Davenport v Greer: ‘Smash and grab’ lives on

Download Publication

‘Smash and grab’ adjudications were predicted to end after last year’s S&T v Grove ruling; the judgement had its first test case earlier this year.

The death knell that many sounded for “smash and grab” adjudications – after a landmark case last year – may have been premature.

The term was coined for an adjudication which follows an employer’s failure to serve a valid pay less notice against either a payment notice or a default notice. As a result of the employer’s failure to issue a pay less notice, the contractor seeks an adjudicator’s decision that the sum stated as due in the payment notice or the default notice is due by default.

Until recently, the Technology and Construction Court (TCC) had made it clear – through the ISG v Seevic and Galliford Try Building v Estura judgements – that where a smash and grab adjudication has occurred, there could not be a subsequent second adjudication by the employer to determine the “true value” of the contractor’s account until its next interim application.

The Court of Appeal subsequently decided, following Harding v Paice, that the principles developed in ISG and Galliford were limited to interim applications only and did not apply to final accounts disputes.

Then came last year’s the S&T v Grove ruling. The Court of Appeal upheld an earlier TCC decision that, following a successful smash and grab adjudication relating to an interim application, the employer is entitled to refer the dispute to a second adjudication to establish the true value of the contractor’s account – but only after paying the sum that was awarded in the first adjudication.

But how would the decision in S&T be applied to final account disputes?

M Davenport Builders v Greer [2019] has provided the answer. Davenport, which had been delivering construction works on a building in Stockport, had made an application for final account, but Greer failed to pay by the final date for payment. Davenport launched an adjudication and was awarded the full amount claimed in its final account application.

Greer then commenced a second adjudication to determine the true value of the account and the adjudicator decided that no sum was due to Davenport as a result of the revaluation. Davenport then began enforcement proceedings in the court and Greer sought to rely on the second adjudicator’s decision that Davenport was not entitled to any money.

Judge Jeremy Stuart-Smith confirmed that, following a smash and grab adjudication, the employer is entitled to refer the true value of the contractor’s final account to be decided by an adjudicator. However, as with the S&T decision, in the Davenport case he ruled that the employer is only able to do so after it has paid the first adjudicator’s decision.

Stuart-Smith said: “The decisions… in S&T v Grove are clear and unequivocal in stating that the employer must make payment in accordance with the contract or in accordance with section 111 of the Amended Act before it can commence a ‘true value’ adjudication.”

This suggests that there is still plenty of life in smash and grabs.


James Sargeant is an associate at Quigg Golden.

Originally published in the April 2019 issue of Construction Manager, available here.

Similar Publications

Published 8 March 2024

#InspireInclusion in Construction Dispute Resolution

Read Publication

Published 27 February 2024

Insight Magazine 51.1

Read Publication

Published 20 February 2024

Material Price Increases – The Red Sea Attacks & How to Protect Yourself

Read Publication

Published 7 February 2024

Conciliation of Construction Disputes by Brian Bond

Read Publication

Sign Up For Our Newsletter

Stay Updated on Our News & Events