Back to Publications

Regulation 73 – Codifying Termination Clauses in Public Sector Contracts

Download Publication

On 26 February 2015, the Public Contracts Regulations 2015 came into force, transposing into UK national legislation European Union Directive 2014/24/EU. Amongst a raft of changes, one aspect that will be of particular importance to the public and private sectors alike is Regulation 73. This places an obligation on contracting authorities to provide arrangements to govern the sometimes uncomfortable relationship between procurement and contract law.

Regulation 73 sets out three scenarios where the contracting authority must be able to terminate the contract of an economic operator:

1. The contract has been subject to a substantial modification which would have required a new procurement procedure.

2. Grounds for exclusion of the economic operator (as defined by the Directive) become applicable.

3. The contract is declared ineffective by a Court.

This is not a change in the law per se as various jurisprudence has created this duty for contracting authorities to terminate when the circumstances outlined above occurred. What Regulation 73 provides for is an obligation for contracting authorities to codify the right to terminate in their contracts. However, the mechanics of how this is to be achieved – notices, payment for loss and expense etc. – is at the discretion of contracting authorities. Further, and in a ‘belt-andbraces’ approach, Regulation 73 states that where a contracting authority has not included provisions for termination on one or more of the three grounds, such a right may be implied.

To assist contracting authorities, Quigg Golden has produced exemplar amendments for two standard forms of contract NEC3 Engineering and Construction Contract and the JCT Standard Building Contract.

The additional condition of contract (Z clause) for use in an NEC3 Engineering and Construction Contract:

Z1 Additional reasons for termination

Insert new line in Termination Table:

Terminating Party  Reason Procedure Amount due
The Employer   R22 – R24 P1 and P4  A1 and A2

Insert new clause 91.8

91.8 The Employer may terminate if:

–  The effect of a compensation event is to substantially modify the contract within the meaning of Regulation 73 of the Public Contracts Regulations 2015 and the Employer is required to initiate a new procurement procedure (R22).

– The Contractor, including any person employed by the Contractor in an administrative, management or supervisory role and including any person who has powers of representation, decision-making or control within the Contractor, becomes the subject of a conviction for one of the reasons set out in Regulation 57(1) of the Public Contracts Regulations 2015 (R23).

– The contract is declared ineffective by a review body in accordance with Regulation 98(2) of the Public Contracts Regulations 2015 (R24).

If a JCT Standard Building Contract is used, the proposed amendment is:

Add new clause 8.6A 8∙6A The Employer may by notice to the Contractor terminate that employment:

∙1 If the effect of any adjustment to the Contract Sum in accordance with clause 4∙3∙1 or the effect of any adjustment to the Completion Date in accordance with clause 2∙28 is to substantially modify the contract within the meaning of Regulation 73 of the Public Contracts Regulations 2015 and the Employer is required to initiate a new procurement procedure.

∙2 The Contractor and/or the Contractor’s Persons (including any person employed by the Contractor in an administrative, management or supervisory role and including any person who has powers of representation, decision-making or control within the Contractor) becomes the subject of a conviction for one of the reasons set out in Article 57(1) of the Public Contracts Regulations 2015.

∙3 The contract is declared ineffective by a review body in accordance with Regulation 98(2) of the Public Contracts Regulations 2015.

Amend clause 8∙7 Delete “8∙5 or 8∙6” at the end of the sentence and replace with “8∙5, 8∙6 or 8∙6A”

Amend clause 8∙7∙5 Delete the word “shall” in the middle of the sentence and replace with “may”. Delete the words “or, if that sum is less, by the Employer to the Contractor”

Main Contractors should also be aware of this issue if they contract with public sector bodies. Quigg Golden’s recommendation is that contracts entered into should have ‘back-to-back’ provisions in a similar form to the above.

For further information, please do not hesitate to contact us.

Similar Publications

Published 8 March 2024

#InspireInclusion in Construction Dispute Resolution

Read Publication

Published 27 February 2024

Insight Magazine 51.1

Read Publication

Published 20 February 2024

Material Price Increases – The Red Sea Attacks & How to Protect Yourself

Read Publication

Published 7 February 2024

Conciliation of Construction Disputes by Brian Bond

Read Publication

Sign Up For Our Newsletter

Stay Updated on Our News & Events