
Disclaimer
These questions and answers are for general information and
guidance only. They should not be relied on in particular situations
without contacting Quigg Golden and receiving detailed advice.
How does the Construction Act 1996 or Construction Contracts (Northern
Ireland) Order 1997 affect us?
The Order provides certain rights to parties to a construction
contract in respect of payment. If you keep an eye on these, you
will improve your cashflow. These are:
• For payment by instalments or stage payments for contracts
over 45 days duration;
The Order now regulates the provisions which must be found in construction
contracts both standard form and those that you have drafted yourselves.
Article 8 of the Order states that unless the duration of the works
are to be for less than 45 days contracts must provide for stage
or other periodic payments.
• To be informed of the amount to be paid in any instalment
and when it is due for payment and the basis on which any amount
is calculated;
The Contract must provide a mechanism for determining what payments
become due, when these are due and what the final date for payment
is. Article 9 of the Order means that the payee must now specify
the amount of the payment to be made or proposed to be made within
5 days of the date on which a payment becomes due.
• To be given notice if it is intended that any payment
be withheld;
Article 10 of the Order provides that payment may not be withheld
after the final date for payment unless the payee has given a Notice
of Intention to Withhold Payment.
• The right to suspend performance if payment is not made
within a specified period; and
Article 11 of the Order gives a right to suspend performance for
non-payment if monies due under the Construction Contract are not
paid in full by the final date for payment and no Notice to Withhold
has been given.
• The outlawing of pay when paid clauses
Article 12 of the Order prohibits pay when paid clauses except
where a person from whom the payer is receiving payment is insolvent.
If your contract does not comply with the Order then the Scheme
for Construction Contracts Part 2 applies. By way of the Scheme
for Construction Contracts the Order makes provision for the referral
of a dispute arising under a construction contract to adjudication.
How to use the Construction Order to help, and what is needed?
The Construction Order is supposed to help you by making bills
more certain to be paid and making disputes easier to settle. The
measures that were introduced to ensure this were:
• new rules to make payment fairer;
• the right to suspend work for non-payment;
• the introduction of Adjudication.
If your Contract doesn't allow for these then the Scheme for Construction
Contracts will kick in.
In order to get the Construction Order to help you, you need to
exercise your rights under points 1, 2 and 3. We will deal with
them individually.
New rules to make payment fairer
Under Article 12 of the Order pay when paid clauses are now banned
unless the third party is insolvent. Your money cannot be withheld
due to a pay when paid clause. This is illegal and you must take
action if the payee attempts to do this. As we indicated at the
previous section, main contractors may try and get around this by
including pay when certified clauses in the Contract, such a clause
should not be agreed, when entering the contract initially.
Under Article 9 (2) of the Order the payer must now issue a notice
within 5 days of the due date, identifying what will be paid, what
the payment relates to, and on what basis it has been calculated.
If you do not agree with the calculations you must write and give
your reasons.
Construction contracts must now provide a final date by which each
interim payment has to be made. The Scheme specifies 17 days from
the due date. There are two main points here. Firstly, you should
mark on a calendar when you are due payment and follow it up. Secondly,
object strongly when formulating a contract if the contract contains
a period longer than 17 days from the due date when a payment must
be made or if it tries to alter the due date disadvantageously.
Under Article 10 of the Order parties intending to withhold payment
must give notice that they intend to do this and reasons for their
actions. The notice period may be a period specified within the
contract, otherwise it will be 7 days under the Scheme. If no notice
is received, payment cannot be withheld. Take action!
The right to suspend work for non-payment
Under Article 11 of the Order you now have the right to suspend
work if payment has not been met by the final date for payment and
no withholding notice has been issued. 7 days notice of intention
to suspend must be given. Think about exercising these rights as
long as you are satisfied that you are exercising them within the
Contract. Object to entering into a contract where the other party
wishes to extend the notice period beyond the 7 days given under
the Scheme.
Top of Page
|