
Disclaimer
These questions and answers are for general information and
guidance only. They should not be relied on in particular situations
without contacting Quigg Golden and receiving detailed advice.
How important is a programme?
Apart from being an essential planning tool for any construction
project, programmes can have a specific contractual meaning. The
most important programme, but also one of the most unusual, is a
programme which actually forms part of the contract. This is a two
edged weapon, since if any dates shown on a contract programme are
not achieved then the contractor is automatically in breach of contract.
One important programming item which is almost always included in
the contract is a completion date. This is described in clause 23
of JCT 98; and in clause 43 of the ICE 6th Edition.
During the tender process it is good practice for the contractor
to draw up a tender programme. This does not form part of the contract
but is usually used by the contractor to estimate the contract duration
and the critical elements and sequence for the Works. If the programme
is detailed with reference to each part of the contract, it becomes
of tremendous importance whenever the job begins to change as a
result of changes by the Client, actions of the others on site,
or unforeseen weather or ground conditions. This tender programme
is commonly used by contractors to show how they had originally
intended to do the work and consequently, when compared with an
as-built programme or progress programmes, shows how much they have
been prevented in using the method of work they had intended to
complete the works as planned. This is a very important tool in
establishing a claim for loss and expense because of disruption
to the works or for attempting to prove an extension of time or
acceleration claim. How accurate this tender programme is, very
much depends on the priority allocated to it at tender stage, the
skill of a contractor’s estimator and the ability to accurately
reflect the elements of the work on paper. Whilst this will cost
money for preparation, management or administration without careful
preparation these costs will be subsumed by the cost of preparing
a claim and the undoubtedly lesser amount that will be recovered.
After all, the side with the better record wins.
The contractor must base his rates and contract sum on something.
It, therefore, should not come as a surprise to clients or their
professionals that whenever changes occur in the progress of the
works, it costs the contractor money or has a cost implication.
These are costs that clients must be prepared to pay. Most contracts
have a mechanism for allowing the contractor to recover losses incurred
in this way.
It is therefore vitally important that tender and successive programmes
are carefully maintained and inter-related as the work progresses.
The importance of these is often lost in the thick of battle during
the contract.
What rates and prices can we use to price variations?
The “normal” way to value variations is to use bill
of quantities rates. The usual rules are:
• where the varied work is of similar character to, is executed
under similar conditions as, and has not significantly changed the
quantity of, works set out in the contract rates and prices for
the work the rates are to be used.
• where the varied work is not then the rates and prices for
the work shall be the basis for determining the valuation; or
• where the varied work is not of similar character, it shall
be valued at fair rates and prices.
Helpful guidance on the valuation of variations under an ICE contract
has been given in the case of Weldon Plant Limited - and - Commission
for New Towns.
Two questions beg to be asked:
• When is it reasonable to apply Bill Rates? Where a Contractor
has a particularly good set of rates and the work has not substantially
changed he can rely on these for valuations of variations. The corollary
being that if the Contractor has under priced a rate item he is
also stuck with this regardless of whether it is advantageous the
Employer. The rules are contract specific.
• What is a fair valuation?
In answering the first of these questions it has been said:
"So too is an Employer stuck with rates and prices which have
been accepted by him as part of the Contract. Unless the Contract
permits, he cannot extricate himself from the bargain that has been
made."
Change valuation under the NEC Contracts is different.
Top of Page
|