
Disclaimer
These questions and answers are for general information and
guidance only. They should not be relied on in particular situations
without contacting Quigg Golden and receiving detailed advice.
What is the significance of having a record of when we started
and finished?
Accurate and objective records on when work started and stopped
are of great benefit for everyone. This sort of basic but fundamental
record is often surprisingly badly kept. Don’t let this happen!
To recover money at the claims stage! The contract price will almost
definitely be based in part on how long it is intended that the
job will take. This is on the premise that if the job takes longer
it will cost more. A record of when you started and finished will
be invaluable when formatting a claim for disruption/delay/prolongation
or loss and expense. In order to prove how effectively you carried
out the work, you will also need records of when you started and
finished each part of the contract. One essential record for both
the offensive and defensive action is a programme.
How important is a programme?
Apart from being an essential planning tool for any construction
project, programmes can have a specific contractual meaning. The
most important programme, but also one of the most unusual, is a
programme which actually forms part of the contract. This is a two
edged weapon, since if any dates shown on a contract programme are
not achieved then the contractor is automatically in breach of contract.
One important programming item which is almost always included in
the contract is a completion date. This is described in clause 23
of JCT 98; and in clause 43 of the ICE 6th Edition.
During the tender process it is good practice for the contractor
to draw up a tender programme. This does not form part of the contract
but is usually used by the contractor to estimate the contract duration
and the critical elements and sequence for the Works. If the programme
is detailed with reference to each part of the contract, it becomes
of tremendous importance whenever the job begins to change as a
result of changes by the Client, actions of the others on site,
or unforeseen weather or ground conditions. This tender programme
is commonly used by contractors to show how they had originally
intended to do the work and consequently, when compared with an
as-built programme or progress programmes, shows how much they have
been prevented in using the method of work they had intended to
complete the works as planned. This is a very important tool in
establishing a claim for loss and expense because of disruption
to the works or for attempting to prove an extension of time or
acceleration claim. How accurate this tender programme is, very
much depends on the priority allocated to it at tender stage, the
skill of a contractor’s estimator and the ability to accurately
reflect the elements of the work on paper. Whilst this will cost
money for preparation, management or administration without careful
preparation these costs will be subsumed by the cost of preparing
a claim and the undoubtedly lesser amount that will be recovered.
After all, the side with the better record wins.
The contractor must base his rates and contract sum on something.
It, therefore, should not come as a surprise to clients or their
professionals that whenever changes occur in the progress of the
works, it costs the contractor money or has a cost implication.
These are costs that clients must be prepared to pay. Most contracts
have a mechanism for allowing the contractor to recover losses incurred
in this way.
It is therefore vitally important that tender and successive programmes
are carefully maintained and inter-related as the work progresses.
The importance of these is often lost in the thick of battle during
the contract.
How do I recover money by claims?
The first step, is to claim everything that is due to you. In practice,
the amount that you will recover will depend not only on when you
submit a claim, but also on your evidence. This highlights the importance
of good record keeping. Often you will have a claim for something
without realising it. Potential heads are:
• variations;
• unforeseen events;
• delay caused by design team;
• error in documentation;
• tendering process;
• sub-Contractors;
• others.
A well thought out and well prepared claim, can include any or
all of these heads and bring in substantial rewards. In a claim
you may recover:
• straight forward monetary loss i.e. full recovery for any
measured work or variations;
• retention;
• wrongfully deducted discounts;
• damages for breach of contract;
• interest;
• the costs of the claim;
• an extension of time is also a valid head of claim and will
not only be the foundation for claims where there has been a time
element, but will also help to protect you against any claims against
you for ascertained or general damages.
None of the above will be recovered unless you take action, and
take it promptly.
What is completion?
When a building is practically complete varies, not only between
Architect and Contractor, which you would
expect, but also varies between Architects.
The key tests to decide whether or not a building is practically
complete must include:
• does everything work in the manner it is intended to, subject
to minor adjustment?
• does the building serve its intended function?
• will any further work necessary not cause undue disruption
to the occupants of the building?
If the answer to these questions is "Yes",
then the building is probably practically complete.
Top of Page
|