
Disclaimer
These questions and answers are for general information and
guidance only. They should not be relied on in particular situations
without contacting Quigg Golden and receiving detailed advice.
How do I recover money by claims?
The first step, is to claim everything that is due to you. In practice,
the amount that you will recover will depend not only on when you
submit a claim, but also on your evidence. This highlights the importance
of good record keeping. Often you will have a claim for something
without realising it. Potential heads are:
• variations;
• unforeseen events;
• delay caused by design team;
• error in documentation;
• tendering process;
• sub-Contractors;
• others.
A well thought out and well prepared claim, can include any or
all of these heads and bring in substantial rewards. In a claim
you may recover:
• straight forward monetary loss i.e. full recovery for any
measured work or variations;
• retention;
• wrongfully deducted discounts;
• damages for breach of contract;
• interest;
• the costs of the claim;
• an extension of time is also a valid head of claim and will
not only be the foundation for claims where there has been a time
element, but will also help to protect you against any claims against
you for ascertained or general damages.
None of the above will be recovered unless you take action, and
take it promptly.
How can we reduce the effects of deductions from our account for
discount and retention?
All too often we see cases where discount and retention have been
wrongly deducted from contract sums. In fact, it is so universally
accepted it seems like the industry norm. This shouldn't be the
case! Contractors should avoid offering discounts and negotiate
low rates for retention from the outset, as both impact severely
on cashflow and profitability. We will take discount and retention
in turn.
What is a contractual discount?
Some contractors/sub-contracts provide for the employer/contractor
to be entitled to a discount upon certain conditions being fulfilled.
This provides a classic example of the importance of reading the
Contract.
To take DOM/1 As an example, Amendment 10 changed the rules regarding
discounts and was issued in 1998.
Before Amendment 10, the mechanism for payment under DOM/1 was
detailed at Clause 21. Clause 21.3.2 provides expressly that the
discount can only be made if the contractor complies with the payment
obligations; in that payments are made within 17 days of the date
due. If the contractor does not comply with the provisions of the
sub-contract in respect of the payment dates, then discount cannot
be deducted which would entitle the discount to be claimed back
together with interest.
In not allowing the deduction of discount, a sub-contractor minimises
his exposure to making a loss. Furthermore, it reduces his break
even point on the project, increasing the opportunity to make money
and become profitable.
A much more difficult question is whether the contractor has to
comply with the obligation every month before he can deduct the
discount from the total. If a payment in one month is made late,
is it simply the percentage reduction in relation to that month
that can not be made or does the contractor lose his right to deduct
any discount at all? In any event, it is essential to track times
of payment in discount circumstances.
The percentage of discount identified in the Articles of Agreement
Part 7 is 21/2%, unless a different percentage is inserted. A lower
rate should always be negotiated because why is a discount being
given? It should not be because of habit or custom.
The edition of DOM/1 which incorporates Amendment 10, however,
is totally different It does not provide for payment terms to be
met for the discount. Therefore unless this has been specifically
amended, the Contractor is always entitled to deduct discount.
It is therefore vital to not only know which standard provisions,
if any, is incorporated into the sub-contract but also which edition
and which amendments are incorporated.
The right to deduct discount applies to all payments whenever made
and may be lost by late payment, but this would depend on the specific
terms of the contract/sub-contract.
If the discount is related to prompt payment, then is each payment
considered in isolation, or if one payment is late is no discount
allowed whatsoever? Once again, need effective procedures are needed
to monitor when payments are due, and to check whether or not the
contractor/employer should be deducting any discount at all. Also
ensure you have a standard letter to send out if discounts are deducted
although payments are made late.
When discounts are taken ensure that they are not deducted before
retention is deducted. If the opposite is carried out it would equate
to giving the employer/contractor a large figure for discount -
not a good idea if you are trying to improve your cashflow or profitability.
How do we deal with retention?
Every standard form of contract in the construction industry has
some form of provision for retention or reserve. As with all issues
like this, the starting point is to look at the contract and find
out what it actually says.
DOM/1 is a typical contract, the provision for dealing with retention
is at Clause 21.5 which provides:
• up until Practical Completion, the Contractor can deduct
the percentage which is stated in the Articles of Agreement. The
Articles of Agreement provide that if no percentage is inserted
it will be 5%. In many instances this rate may be negotiated to
3%. It is worthwhile providing evidence that a percentage of 5%
is not required from previous projects completed within a 6 year
period.
• although the reduction in the retention percentage may appear
minimal, it may have a disproportionate impact on a contractor's
profitability. When you consider 2% of £X thousands of pounds
retained by the employer/contractor over the period of the contract
and 12 months after Practical Completion of the works. Example contract
sum £300,000.00, retention at 5% and 3% will be £15,000.00
and £9,000.00 respectively, a difference of £6,000.00
over a possible period of 2 years. Thus, a 2% reduction would make
available to a contractor an extra £6,000.00, which should
be working for him.
• upon practical completion but before a Certificate of Completion
of Making Good Defects is issued, only one half of the percentage
of retention can be deducted. Ensure you have a calendar marked
with dates on which retention should be requested and take action
on those dates as they occur.
• upon the issue of a Certificate of Completion of Making
Good Defects, all retention monies are to be released, by way of
an interim payment, to the contractor. Again this date should be
marked on your calendar as two dates, when to request the release
and when to receive payment.
Remember that if a contract or sub-contract does not make specific
provision for retention then the employer/contractor has absolutely
no right to withhold retention. If retention is provided for, the
percentage and release dates may vary accordingly. First check if
the contract allows for the taking of retention, and secondly check
the rate of percentage. Negotiate a lower rate where possible. Lower
rates add substantially to the profitability of a contractor.
In some instances a contractor/sub-contractor can wait for the
release of retention for long periods after the works have been
completed. Use effective procedures to chase these monies on a regular
basis. It may only take a few letters and threats of adjudication
or arbitration. These actions may only be minor but accumulatively
they add substantially to the profitability of a company and its
cashflow.
It is our experience that retention and percentages of retention
are accepted as standard issues in most contracts. This general
acceptance should not be the norm and should be challenged whenever
the issue arises. It is particularly unfair to groundwork sub-contractors
or structural steel sub-contractors who may complete their works
long before practical completion of the main contract. If they have
to wait a very long time for release of retention on large sums,
this may have a disastrous impact on cashflow and profitability.
In such circumstances, it is definitely worthwhile negotiating for
a lower rate or zero retention where possible. In some instances
the monies involved in retention equate to the profit on the project.
It has recently be described as unfair in the in the UK by the
House of Commons Report “Construction Matters” printed
on 8 July 2008.
How can we ensure that we get the final payment once we have finished
our works?
In order to remain profitable and improve cashflow, contractors
should make prompt and comprehensive applications for payment as
soon as the first payment becomes due and make sure that all dates
for subsequent applications are met! Therefore it is good practice
to ensure that the final payment is treated in the same way as all
previous payments should be and apply promptly for the outstanding
payment due.
The main difficulty with final accounts is not lack of understanding
of the contractual provisions, as these are relatively straight
forward. The real problems are as follows:
• since the work has already been carried out there is no
incentive for payment to be made.
• Unlike interim payments contractors/sub-contractors do not
have the commercial weapon of threatening to walk off site unless
payment is made.
• too often, the final account is successfully fudged off
for many months, even years. Staff come and go, and the contractor/sub-contractor
soon finds himself chasing payment for work which was carried out
many years ago.
• the final account should be put together or built up from
day one, on and off site. It is important to have effective procedures
in place to put together all the relevant information and documentation
to substantiate the monies you assess as being due to you.
Final payment needs to be applied for as soon as it is allowed
under the Contract. Why have the money sitting in someone else's
bank account gaining interest, when it could be sitting in yours?
The date for application is likely to be regulated by the construction
contract. For example the DOM/1 form of Sub-Contract provides that
the sub-contractor is to send to the contractor all documents necessary
for the adjustment of the sub-contract sum (final payment) within
4 months of practical completion of the sub-contract works (sub-contract).
The final payment is then due within 7 days of the issue of the
final certificate by the architect under the Main Contract. Before
the date for final payment the contractor must send the sub-contractor
a notice informing him of the amount of payment which the contractor
believes is due to the sub-contractor. If the sub-contractor does
not agree with the amount, he must write and put his position forcibly
giving reasons. Such reasons would include alternative calculations
for the monies due, correspondence detailing the claim and any action
proposed to be taken. Like DOM/1 every standard form construction
contract will:
• provide a date for final payment;
• require the payee to issue a notice indicating that payment
is intended to be withheld if this is the case.
Final Payment
Where the Scheme for Construction Contracts applies, the date for
final payment is taken from this. It is well worth calculating this
date as early as possible in order that a prompt application might
be made. The final payment will become due according to paragraph
5 of the payment provisions in the Scheme, namely on the expiry
of 30 days following completion of the works or on the making of
a claim by the payee whichever is the latest.
How do we deal with a withholding notice?
If you are on the receiving end of a withholding notice and you
do not agree with what is being withheld, object! It will help your
case later. If no withholding notice is issued, this is contrary
to the Order.
Make sure that you have all of your documents together to make
a claim promptly after completion. The earlier your claim is in
the mind of the payer the more quickly you may resolve difficulties.
It is a good idea to keep all relevant records from day 1 in order
that you can fully substantiate the monies due to you at an early
stage. We will be discussing records and emphasising the importance
of keeping them throughout this seminar.
Of course it bears repeating, that as initially stated, you will
find it more difficult to get your final payment, and will not help
your cashflow and profitability overall if you do not take a no-nonsense
approach to all money due to you. Interim payments should be applied
for promptly under the Contract and followed up if they are not
received. There are provisions in the standard form or contracts
for application for these just as there are for final payment. These
may be found at clause 21 of DOM/1, clause 30.1 of JCT’98
and paragraph 4 of the Scheme.
When is the first half of the retention money released?
Most people expect the answer to be very simple as it is either
released on Practical Completion for JCT Contracts or at Substantial
Completion for ICE Contracts. This, of course, is true but it ignores
the fact that many contracts are not in those forms or that there
may be no provision for the deduction of retention monies at all.
The position is much more complicated with sub-contracts. Many
sub-contracts do not provide for retention and material suppliers
will rarely allow for retention in their standard terms and conditions.
Those sub-contracts which do provide for retention may either provide
that the first half is released at practical completion of the main
contract works, or is released when the sub-contract works are substantially
complete. There can be a long time between those two dates. When
negotiating at the tender stage, where possible express a release
of retention when the sub-contract works are substantially complete
and not on practical completion of the main contract works. These
are strategies to improve cashflow and profitability. Individually
these steps may appear small, but cumulatively over many contracts
they may have substantial impact on getting paid, cashflow and profitability.
Thus, the terms of the contract will decide what event triggers
the release. The most common event is practical completion but that
in turn introduces a level of uncertainty because practical completion
is often not clearly defined.
When is the final release of all retention monies?
The only money which the Employer is entitled to hold after Practical
Completion is the retention money. If the Certificate of Completion
of Making Good Defects has been issued under a JCT form, then the
second half of the retention must be released.
If there are defects apparent at any stage up to the issue of the
Certificate of Practical Completion, then either the employer does
not pay for that part of the work which is not done properly, or
the Certificate of Completion of Making Good Defects is not issued.
If there is a suspicion of latent defects, it would be very prudent
to have an investigation done prior to the end of the defects liability
period.
Where there are no suspicions of latent defects and withholding
retention is merely an insurance in case of latent defects, then
the Employer does not have authority to do this. If Employers wished
to amend the JCT Contract to protect against such situations, it
would be quite easy to do so. For example the retention could be
released at the end of six years. Contractors should resist such
a move vigorously, as it does not make good commercial sense and
definitely does not assist in the profitability or the company's
cashflow.
If an Employer felt that the retention was not a sufficient amount
of money, then the sum being held could be increased by amending
the contract to 10% as is very common overseas. This might have
an effect on tender prices in that tenders would be higher and have
a higher percentage for profit and overheads to reflect the greater
liability being undertaken by Contractors.
Can they set-off monies due on one job from monies outstanding
on other jobs?
Sir Michael Latham recommended in his famous report "Constructing
the Team" that one unfair contract clause which needed to be
outlawed was that which purported to set-off in respect of any contract
other than the one in progress. Unfortunately this is still done.
In the absence of an express contractual term, Contractors and Employers
cannot set-off monies from another job other than the one that you
are undertaking. This is because the two different jobs will presumably
be covered by two separate contracts. The right to set-off arises
under the Contract. However, Contractors/Employers are getting around
this by inserting terms into the Contract allowing set-off from
other jobs. If you have agreed to this you cannot object! The moral
is not to agree to such a term when negotiating. After all, whose
benefit is this term for?
Any set-off is subject to the Notice of Intention to Withhold that
we have discussed. Regardless of what is in the Contract, if you
do not agree with what is being set-off you must object in writing.
Once monies have been set-off it is difficult to get them back.
Whilst it may be commercially difficult, pursue it.
How do we deal with deducting monies for contra charges?
Contra Charges & Set-Off
Set-off is the single biggest source of dispute between Employers,
Contractors and Sub-Contractors. This is because contractors/sub-contractors
claim that employers/contractors deduct money for insufficient reason
or for no reason at all. The effect in many instances making a profitable
project break even or even worse making a project at final account
stage into a loss making project. If Employers/Contractors are deducting
money, you need to be sure at the outset that they are following
the correct procedures. If they are not, they can't deduct money
from your account.
How does the Construction Act 1996 or Construction Contracts (Northern
Ireland) Order 1997 affect us?
The Order provides certain rights to parties to a construction
contract in respect of payment. If you keep an eye on these, you
will improve your cashflow. These are:
• For payment by instalments or stage payments for contracts
over 45 days duration;
The Order now regulates the provisions which must be found in construction
contracts both standard form and those that you have drafted yourselves.
Article 8 of the Order states that unless the duration of the works
are to be for less than 45 days contracts must provide for stage
or other periodic payments.
• To be informed of the amount to be paid in any instalment
and when it is due for payment and the basis on which any amount
is calculated;
The Contract must provide a mechanism for determining what payments
become due, when these are due and what the final date for payment
is. Article 9 of the Order means that the payee must now specify
the amount of the payment to be made or proposed to be made within
5 days of the date on which a payment becomes due.
• To be given notice if it is intended that any payment
be withheld;
Article 10 of the Order provides that payment may not be withheld
after the final date for payment unless the payee has given a Notice
of Intention to Withhold Payment.
• The right to suspend performance if payment is not made
within a specified period; and
Article 11 of the Order gives a right to suspend performance for
non-payment if monies due under the Construction Contract are not
paid in full by the final date for payment and no Notice to Withhold
has been given.
• The outlawing of pay when paid clauses
Article 12 of the Order prohibits pay when paid clauses except
where a person from whom the payer is receiving payment is insolvent.
If your contract does not comply with the Order then the Scheme
for Construction Contracts Part 2 applies. By way of the Scheme
for Construction Contracts the Order makes provision for the referral
of a dispute arising under a construction contract to adjudication.
How to use the Construction Order to help, and what is needed?
The Construction Order is supposed to help you by making bills
more certain to be paid and making disputes easier to settle. The
measures that were introduced to ensure this were:
• new rules to make payment fairer;
• the right to suspend work for non-payment;
• the introduction of Adjudication.
If your Contract doesn't allow for these then the Scheme for Construction
Contracts will kick in.
In order to get the Construction Order to help you, you need to
exercise your rights under points 1, 2 and 3. We will deal with
them individually.
New rules to make payment fairer
Under Article 12 of the Order pay when paid clauses are now banned
unless the third party is insolvent. Your money cannot be withheld
due to a pay when paid clause. This is illegal and you must take
action if the payee attempts to do this. As we indicated at the
previous section, main contractors may try and get around this by
including pay when certified clauses in the Contract, such a clause
should not be agreed, when entering the contract initially.
Under Article 9 (2) of the Order the payer must now issue a notice
within 5 days of the due date, identifying what will be paid, what
the payment relates to, and on what basis it has been calculated.
If you do not agree with the calculations you must write and give
your reasons.
Construction contracts must now provide a final date by which each
interim payment has to be made. The Scheme specifies 17 days from
the due date. There are two main points here. Firstly, you should
mark on a calendar when you are due payment and follow it up. Secondly,
object strongly when formulating a contract if the contract contains
a period longer than 17 days from the due date when a payment must
be made or if it tries to alter the due date disadvantageously.
Under Article 10 of the Order parties intending to withhold payment
must give notice that they intend to do this and reasons for their
actions. The notice period may be a period specified within the
contract, otherwise it will be 7 days under the Scheme. If no notice
is received, payment cannot be withheld. Take action!
The right to suspend work for non-payment
Under Article 11 of the Order you now have the right to suspend
work if payment has not been met by the final date for payment and
no withholding notice has been issued. 7 days notice of intention
to suspend must be given. Think about exercising these rights as
long as you are satisfied that you are exercising them within the
Contract. Object to entering into a contract where the other party
wishes to extend the notice period beyond the 7 days given under
the Scheme.
The introduction of adjudication
Any construction contract under the Order, with very few exceptions,
may go to adjudication. If you are not paid on time and paid in
full, use it! Adjudication is a faster and cheaper dispute resolution
method that arbitration or litigation. Make sure that you have a
dispute or difference and give notice of your intention to refer
a dispute to adjudication under Article 7 of the Order. This right
may be exercised at any time. When forming the Contract, it is worth
thinking about naming a "good adjudicator". This will
satisfy you that you have somebody capable at the helm if a dispute
does get this far.
Does arbitration Work?
Arbitration certainly produces results in more complex cases. As
more time and preparation goes into arbitration, it has not received
the level criticism that adjudication has. It has further benefit
in that it provides more finality.
Top of Page
|